Monthly meeting 24.03.2010

Here are the outcomes of the discussed topics from today’s project monthly meeting.

Discussed:

* Review of progress to date:

  • have done the problem analysis, use case scenarios, requirements analysis, and specification
  • working on the demonstrator design
  • started looking into technical issues that may affect the design

* Review of progress against the work plan submitted to JISC – Progress OK, a bit behind, but will catch up soon:

  • have completed the workpackage1, the demonstrator requirements and specification (but haven’t put it on project website yet)
  • still working on the workpackage2, the demonstrator design – we are behind on this task!
  • have started investigate required technique for the code library that indentified in the design process – we are ahead on this task!

Actions:

* David:

  • backup plan if Tao can’t come back on time
  • make sure everything is in the blog and wiki
  • check completion report requirements
  • budget tracking

* Lisha

  • Check licensing, IPR
  • Note dependencies (using other code libraries)
  • Technical documentation (e.g. javadoc, XCRI)
  • Provide source & jar file
  • Design docs, UML diagrams
  • Demonstrator: web application or stand alone?
  • Test plan – should be ready to present at April’s monthly meeting

* Tao

  • Coding + documentation