As we enter our second month of the project, here’s a little more background.
The project is funded to the tune of £10k. iSolutions work on integrating ORCID with our systems will account for £5k, with another £2k for work on ePrints. The remaining £3k will cover staff costs in the Library related to management of the project. The cost of ORCID membership will be borne separately by the Library.
Timescales are tight and we are currently looking at the best ways to roll out ORCID membership and beginning to engage with the acdemic community to raise awareness of the project.
Task name | Duration | Start | Finish |
Investigate ID roll out options | 43 days | 01/05/14 | 30/06/14 |
Deliver ID roll out | 66 days | 01/07/14 | 30/09/14 |
ORCID examples in HR database | 89 days | 01/07/14 | 31/01/15 |
ORCID examples in ePrints | 89 days | 01/07/14 | 31/10/14 |
Engagement with NCS | 176 days | 02/06/14 | 31/01/15 |
Engagement with all researchers | 176 days | 02/06/14 | 31/01/15 |
Engagement with equipment.data group | 176 days | 02/06/14 | 31/01/15 |
Coms with other projects/wider community | 198 days | 01/05/14 | 31/01/15 |