Mar 15 2012

Project Gantt Chart

Gantt Chart 1:

This project Gantt chart was completed as an initial one on 27th, February, 2012. 16 tasks from “Welcome and project brief” to “Overview of pitch to dragons den panel” were arranged over two and a half months from 25th, February to 11th, May.

Gantt Chart 2:

This project Gantt chart was completed on 17th, April, 2012, which is an up to date Gantt chart for our project. Please notice that a new task is added to our project, which is “Consideration of Contextual Factors”, describing the aspects of social, economic, privacy and legal of our project. The time duration of the project remains the same. But time scales for most tasks are quite different from the initial Gantt chart.